Sitting and Waiting

Today it is raining but the forecast is that it will clear up this afternoon. That is good as I really need to get outside to continue work on my latest project which is to install permanent electricity to three of the ponds.

The first pond that I built more than 30 years ago was around 2500 gallons and actually looked very nice with a patio that surrounded the entire pond. It developed a leak and even by letting the entire pond drain down to nothing, I was still unable to locate it to make a repair. By then I was hooked on Ponding and I decided to rebuild the pond and at the same time, enlarge the entire thing. The end result is a 5000 gallon pond. I did this one right and it has a permanent electrical supply to it.

100_0268-2

5000 Gallon Pond

I spent the next 30 years messing around building other ponds and streams sometimes even rebuilding because of a change of heart or of different ideas. Because of my restlessness and having a very hard to please attitude, I never installed permanent electricity to any of the 3 other ponds for good reason. For example, the middle pond was actually 2 ponds in the shape of an “L” with water from the top pond filtering down to the bottom pond and then recirculating back to the top pond.
Double Pond 1-2

The original “L” shaped pond

The smaller of the two ponds in this system developed a leak so I decided to separate them into two ponds which meant installing a Sanyo skimmer and another pump on the upper pond. I completely rebuilt the lower pond and installed a new liner and increased the depth to almost 4 feet. It too has its own skimmer box and pump. The electricity to drive the pumps was supplied by lead chords and temporary outlets and worked very well and I kept telling myself that as soon as I was satisfied with the ponds themselves, I would change the setup to something more permanent. Besides, I lived alone with no desire for any sort of company other than my dogs and reasoned that I would be careful as I worked the yard.

I had other water feature that I had built, one in the shape of a “Y” with two streams running into a small pond. This one actually worked pretty well but again, only had temporary electricity to drive the pumps. In a fit of madness, I decided to enlarge the pond at the end of the streams which eventually led to me taking out one stream completely along with the small pond. The end result was a 6000 gallon large pond, quite a bit larger than the 1000 gallon pond it replaced. I kept the one small stream and it still runs very nicely. Throughout all of this building and rebuilding, the electricity to drive the pumps was all supplied through the same system as outlined above, lead chords and temporary outlets.
New Pond 2 5-3-2014

The New 6000 Gallon Pond

Human Nature being what it is and with everything running smoothly, I moved onto other things and although the thought would cross my mind very occasionally, I never seriously considered doing much about the electric supply to the ponds. Things were working fine so why mess with it. Besides, I had plenty of other things to do that seemed to be more important and anyway, I was not in the mood to dig trenches and bury conduit.

Then, a couple of mornings ago, I came out to check on the ponds and everything was very quiet except for the 5000 gallon pond, the one with permanent electricity, that was running just fine. I wandered over to the other ponds and both the “L” shape and the 6000 gallon pond were very still. None of the pumps were working. Luckily, the system can be down for a few hours before any problems are likely to develop in the form of oxygen deprivation and less dangerous but just as frustrating, muddy water. As it is still early Spring, temperatures would not be high enough to really cause oxygen deprivation problems.

I traced the lead chords as they snaked from pond to pond and quickly discovered that the very first chord was scorched where it connected to the next chord. Even as I watched, the next junction suddenly burst into flames. At least I knew where the problems were located and went to work in temporarily replacing the burnt out lead chords with different ones so as to keep the pumps running while I planned out the new permanent power supply.

As luck would have it, years ago, I had installed an outlet by the back porch directly from the Main Junction Box which also happened to be the one that the temporary supply is plugged into. I figured that I could come from that one and then run the wire through conduit to the first of the GFCI outlet boxes that I planned to install. I have two metal boxes that contain two GFCI outlets in each box that I acquired over the years. Bit of an overkill as a single GFCI would protect all of the outlets downline from it but as I happened to have the boxes, why not use them.

So, with a plan in mind, I went to Home Depot and purchased the necessary supplies and to start work on the project. This is actually a three phase project the first of which is to install the conduit from the supply to the location of the first outlet box about 45 feet away. The second phase will be to run the conduit to the second of the outlet boxes another 50 feet further along. The last phase will be to complete the run another 25 feet to the last of the boxes.

I started work on Phase 1 which entailed digging a trench to bury the conduit. This is the hard part of the project mainly because I hate digging and it takes more of a mind set to actually start the work than to do the work. I managed to convince myself that as hot as it was, I needed to get after it. The digging was pretty easy but it did entail swinging a pickaxe to break up the ground, something I haven’t done in years.

The next part of Phase 1 of the project was to lay out the conduit and then pull the cable through each piece before gluing the conduit together. The whole thing was placed into the trench and covered over, with sufficient conduit and cable exposed at each end to make the connections. And that is where we are today and it has just come on to rain again. It doesn’t look like I will be working outside today, darn it…

Look for part two of this thrilling instalment of DIY.

Written 5/20/2018

6 thoughts on “Sitting and Waiting

  1. Your ponds looks beautiful Francis! I enjoyed reading your post though I don’t understand much about the technical bits. I hope you’ll continue and complete your miraculous work as before.

    • Summer is here in Texas and we are close to that magic 100 degree mark everyday. So, work in the mornings outside and then write in my blog when it gets too hot. Thank you for your comments and following along.

    • Yes, but it is 30 years worth of work and I still have other ideas but probably will not work on them. Things are getting harder to work on and the rocks I installed in the past 30 years now seem to weigh twice as much as when I first installed them.

Leave a Reply